203(k) Consultant Fees

Checked against HUD Handbook 4000.1, Update 18 (last revised 8/12/2026) on November 23, 2026.

The Short Answer

HUD sets the most a 203(k) consultant may charge. The Work Write-Up fee runs from up to $1,000 for repairs of $50,000 or less to at most $2,000 for the largest jobs, plus $25 for each additional unit. Each draw inspection is capped at $375, a change order at $120, a reinspection at $225 and a feasibility study at $375. Mileage at the IRS rate can be added when the consultant's business is more than 15 miles from the property.

HUD's Maximum Fee Schedule

These are maximums, not set prices HB 4000.1 II.A.9.c. The schedule in the current handbook (Update 18) took effect with the section dated 11/04/2024.

ServiceMaximum FeeHandbook
Work Write-Up and review of architectural exhibits, repairs up to $50,000$1,000II.A.9.c.ii
Work Write-Up, repairs $50,001 to $85,000$1,200II.A.9.c.ii
Work Write-Up, repairs $85,001 to $140,000$1,400II.A.9.c.ii
Work Write-Up, repairs over $140,0001% of repairs, at most $2,000II.A.9.c.ii
Each additional dwelling unit$25II.A.9.c.ii
Feasibility Study, if the borrower or lender asks for one$375II.A.9.c.i
Each draw inspection (reasonable and customary for the area)$375II.A.9.c.iii
Each change order request$120II.A.9.c.iv
Reinspection of a Work Item, when the borrower or lender asks$225II.A.9.c.v
Mileage, when the consultant's place of business is more than 15 miles from the propertyIRS mileage rateII.A.9.c.vi

Worked Example

A single-family house with $60,000 of repairs, five draw inspections and one change order: the Work Write-Up can be up to $1,200, the draws up to $375 each ($1,875) and the change order $120. The most the consultant could charge is $3,195, plus mileage if it applies.

How the Fees Are Agreed

The consultant and the borrower sign a written agreement that explains the services and the fee for each one. It must also tell the borrower that the consultant's inspection is not a home inspection HB 4000.1 II.A.9.k.ii.

Does This Tell You What Consultants Earn?

No. The schedule caps what can be charged on one 203(k) loan. Income depends on how many jobs a consultant takes and on their other work, which the handbook doesn't address.

Practice This in the Free Course

Module 9, Feasibility Studies and Your Fees covers this with practice questions and a running case file. The course is free, and your progress saves as you go.

Start the Free Course

Roster Ready is independent training based on HUD Handbook 4000.1. It isn't affiliated with, approved by or endorsed by HUD or FHA, and it isn't legal advice. It doesn't recommend or refer lenders, consultants or other providers. The handbook controls: check the cited sections and HUD's current guidance.